ARE YOU LOOKING FOR UNIT 5 MEASUREMENT AND ESTIMATING FOR QUANTITY SURVEYING ASSIGNMENT HELP SERVICE? HIRE SKILLED TUTOR TO BOOST YOUR GRADES!

Qualification - Pearson BTEC Levels 4 and 5 Higher Nationals in Quantity Surveying

Unit Name - Measurement and Estimating for Quantity Surveying

Unit Number - Unit 5

Unit Level - Level 4

Assignment Title - Measurement and Estimating for Quantity Surveying

Unit code - K/618/1768

Learning Outcome 1: Define standard measurement techniques used for taking-off quantities for estimating purposes

Learning Outcome 2: Perform taking-off techniques in the production of a range of quantities for building or infrastructure works

Learning Outcome 3: Interpret the principles and techniques of estimating in compiling a final price

Learning Outcome 4: Prepare an estimate for a work activity

GET BEST RESULTS WITH UNIT 5 MEASUREMENT AND ESTIMATING FOR QUANTITY SURVEYING ASSIGNMENT HELP! HIRE PROFESSIONAL WRITERS TO BOOST YOUR GRADES!

Assignment Brief

Your employment as assistant quantity surveyor in an international quantity surveying practice has commenced. The firm which you work has been appointed by a new client as the client's advisor/ consultant for a foreign funded housing project. This client wants to understand the processes of measurement and estimating and the preparation of estimates throughout a project. Your Senior Quantity Surveyor has asked you to take on the responsibility for developing information to assist the client in understanding this. These will be presented to the client, to provide them with a clear understanding of how you will be undertaking the necessary work for estimating the project costs. Shown below a summary of the tasks which you are requested to perform during this exercise and you will be guided by the Senior Quantity Surveyor with detailed guideline.

» Task 01- Explain the techniques for producing accurate quantities and how a rule of measurement supports this. Comparing different techniques for producing quantities will allow you to critically evaluate an estimating technique and its accuracy.

» Task 02- Using dimension paper, show the taking-off of quantities for a range of construction activities and abstract these. To produce an accurate bill of quantities for a work section, from the design drawings, you will need to apply a standard method of measurement.

» Task 03- To illustrate the way in which labour informs estimates, you will calculate labour unit rates and all-in rates for a range of construction activities and analyze the factor that have an effect on the compilation of unit rates.

» Task 04- Finally, you will present your estimate for a work activity by producing a comprehensive estimate and explain the level of variation in estimates. Comparing the techniques used will allow you to evaluate estimating techniques for the different stages of a project lifecycle.

TASK 01 A
You are requested to provide following for the initial stages of the above project in the report in which will be produced to the client.
» An explanation on the technique that you will use to produce quantities
» Why accuracy is important when using this technique.

The production of accurate quantities is essential in avoiding disputes and claims during the construction stages of a project. International and UK projects' quantities are produced to an agreed format. This format is termed a `Rule of Measurement' and in the UK this is produced by the Royal Institute of Chartered Surveyors.

1A. I Explain the techniques that can be used, both digitally and manually, for the production of accurate quantities for the above housing project. (P1)
1A.2 Critically evaluate an estimating technique to its accuracy in the production of quantities relating to the above project. (DI)
1A.3 Explain how the use of rule of measurement supports the production of accurate quantities. (P2)
1A.4 Compare techniques used for production of quantities against the life cycle of a project. (M1)

MOST RELIABLE AND TRUSTWORTHY UNIT 5 MEASUREMENT AND ESTIMATING FOR QUANTITY SURVEYING ASSIGNMENT HELP & PEARSON BTEC LEVELS 4 AND 5 HIGHER NATIONALS IN QUANTITY SURVEYING ASSESSMENT WRITING SERVICES AT YOUR DOORSTEPS!

TASK 01B
You will be tasked with assembling a bill of quantities (Using NRM2) in tender stage for some of the sections of the housing project based on the information provided below (Part 1Ba, 1Bb and 18c)
Part 1 Ba - Substructure- Appendix la
Part 1 Bb - Superstructure - Appendix lb
Part 1 Bc - External works and Drainage Services - Appendix lc
NOTE - Following tasks are applicable to above Parts 1 Ba, 1 Bb and 1 Be

1B.1 Take-off quantities using standard dimension paper (TDS sheet)/ any digital method by accurately applying standard method of measurement which is specified in the brief for the following elements. (P3) & (M2)

1B.2 Abstract quantities in a standard Abstract sheet for the range of quantities taken-off in task 1 B. I and produce an accurate bill of quantities, using an industry standard format, for the items taken off in part 1B. I above. Bill pages should be processed in spread sheets following the standard format shown in the NRM2.

Following table shows method which should be used in preparation of dimensions sheets, abstract sheets and bill pages.

TASK 02

Your Senior Quantity Surveyor is expecting you to prepare the report based on the information in Task 02A and Task 02B shown below.

TASK 02A
Quoted below an extract from the book Estimating and Tendering for Construction Work by Martin Brook on Analytical estimating.

"Analytical estimating is a method for determining unit rates by examining individual resources and the amounts needed for each unit of work. This method for pricing bills of quantities is described in the CIOB Code of Estimating Practice, in four stages:

1. Establish all-in rates for the individual resources in terms of a rate per hour for labour, a rate per hour for items of plant and the cost per unit of material delivered and unloaded at the site.

2. Select methods and outputs to calculate net unit rates to set against items in the bill of quantities.

3. Add to the net cost project overheads, contingencies, inflation and risk.

4. Summarize resources and prepare reports for management."
a. Calculate the Unit Rate for production of 1 m3 of concrete with 1: 1 1/2 :3 (25mm aggregate)

Pricing Information
» Cost of 1 bag of cement Rs.1175 (including delivery cost)
» Allow 2.5% for residual wastage for cement
» Allow 1 hr unskilled for unloading of 1 metric tonne of cement
» Density of cement 1420 kg/m3
» Cost of 1 m3 of sand R.5.4800
» Cost of 1m3 of metal Rs.3200
» Shrinkage of concrete 50%
» Hiring cost of a concrete mixture Rs.550 per hour (without operator)
» Labour gang-1 Hr operator & 2hrs of loaders(unskilled)

» Labour rates-Skilled Rs.325per hour & Unskilled-Rs.200 per hour

b. Calculate unit rates for the below items extracted form a BQ prepared using NRM2 showing rate breakdowns comprising costs of labour, material and plant etc. You should obtain necessary updated cost information and labour, material, plant requirements from reliable sources (books, published documents etc.) or you may use your won company data for the calculation of rates.

You may use necessary assumptions in calculating the rate and state those in your ansN% ers and use an appropriate format in presenting the rate analysis

2A.1 Calculate unit rates for (a) and (b) details shown above by compiling and processing rate build-up data (P5)

2A.2 Analyze the factors that have an effect upon the compilation of unit rates for an estimate (M3)

TASK 02B

All in rate calculation is required in order to compile a unit rate for a work activity. Refer the following details provided.
a. Labour
All-in rate for Labour

» Basic wage rate : Rs. 8400.00 / week
» EPF/ETF contribution: As per the current applicable percentages
» Accommodation : Its. 2,500.00 / month
» Transport to/from site : Its. 2,000.00 / month
» Medical allowance : Rs. 9,000.00 / year
» Uniforms : Rs. 5,000.00 / year
» Incentives : Rs. 10,000.00 / year
» Annual leave : 21 days per year
» Public holidays : 8 days per year
» Poya days : 12 days per year
» Nonproductive days : 6 days per year
» Working hours to be considered as 8 Hrs per day and 5.5 working days per week.
b. Material

All-in rate for Ceramic Tile
» Purchased price of 1000 ceramic tile Rs 195,000.00 (Tile size 300 x 300mm)
» Allow Rs.625.00 for transportation of 1000 pieces (300 x 300mm) per 1 Km (Distance to site 8 Km)
» Allow three hours of unskilled labour for unloading and stacking 400 pieces
» Allow 3% wastage
c. Plant

All-in rate for Mobile crane
» Capital cost Rs. 105,000,000.00
» Average life of the plant is 4 years

» Scrap value at the end of 4 years Rs. 1,200,000.00
» Insurance premium is 0.3% of the capital value per annum
» Assessed working hours is 10 hours per day for 280 days per annum
» Fuel consumption 4 liters per hour at Rs 130 per liter
» Lubricating oil 10 Liters per month at Rs. 250 per liter
» Tyre2 sets per annum at 150,000 per set
» Periodical services to be done every 500 hours at Rs. 75,000 per service
» All in hourly rate of Operator cost is Rs. 250.00 per hour

2B.1 Calculate all-in rate for labour, material and plant using the information provided in a, b and c above.

You may make reasonable assumptions in your calculations and state the same in your answers (P6)

MIRACLESKILLS.COM OFFERS TRUSTED ADVICE OF WRITER FOR UNIT 5 MEASUREMENT AND ESTIMATING FOR QUANTITY SURVEYING - PEARSON BTEC LEVELS 4 AND 5 HIGHER NATIONALS IN QUANTITY SURVEYING ASSIGNMENT HELP!

TASK 03
Your Senior Quantity Surveyor is expecting you to prepare the report based on the information in Task 01 and Task 03B shown below.

TASK 03A
Appendix 02 shows details of a retaining wall which was not in the original scope of work in an ongoing construction project which consisting of constructing 250 house including development of infrastructure associated with the project. Building works associated with the project is divided among three contractors who are currently engaging with the works. Quotations will be taken from all there contractors for construction of retaining wall (9000mm long).

Instructions:
» You should prepare the measurement sheets using MS Excel and soft copy should be attached with the assignment.
» You may use current market rates in preparing the estimate and attached supportive documents to proof the rates which have been used with properly presenting the alterations made to the date to suit with the requirement

C. You should use SMM7 in taking off quantities

Specifications: Generally
- All details excavations will be started from EGL
- Length of the wall is 9000mm
- EGL to bottom of foundation is 1500mm and thickness of the blinding bed is 50mm
- Height of the Retaining Wall from EGL is 3500mm

Concrete
Blinding bed - Grade 15 concrete
Base and wall - Grade 25 concrete

Formwork
- Basic finish formwork in both substructure and super structure

Reinforcement

- Allow 175kWm3 in all the RC elements

3A.1 Produce a comprehensive estimate for the retaining wall structure (excluding finishes) following the instruction provided in the Task 3A.

3A.2 Explain the reasons for the level of variation in estimates received by stakeholders in the industry even it is being priced for the same project/ activity.

TASK 03B

According to the website architecture (2020), "The RIBA Plan of Work organizes the process of briefing, designing, constructing and operating building projects into eight stages and explains the stage outcomes, core tasks and information exchanges required at each stage". Generally it is required to prepare estimate/ cost plans etc. in all the stages to keep the client updated regarding the project cost.

You may download the RIBA plan of work.

Following Figure 1 (attached) shows the RIBA stages and the formal cost estimating and cost planning stages in context with RIBA plan of work and Figure 2 (attached) shows single rate methods and multiple-rate methods which can be used in cost estimating and cost planning works.

Client wishes to aware of estimating techniques used in costing works in the lifecycle of the project. Further the client wishes to know about the techniques used in estimating final design cost (at a stage which you can provide more accurate estimate for the proposed project). You are requested to perform following tasks by taking the above facts into the account.

3.3 Evaluate estimating techniques used for the different stages of a project's lifecycle by considering the stage stated in the RIBA plan of work - 2007.

3.4 Compare the techniques used for the formulation of budgets with estimating final design costs.

Assessment Criteria

Pass

Merit

Distinction

LO1 Define standard measurement techniques used for taking-off quantities for estimating purposes

D1 Critically evaluate an estimating technique to its accuracy in the production of quantities

P1 Explain the techniques used in the production of accurate quantities

P2 Explain how a rule of measurement supports accurate quantities

M1 Compare techniques used for production of quantities against the life cycle of a project

LO2 Perform taking-off techniques in the production of a range of quantities for building or infrastructure works

D2 Produce an accurate bill of quantities work section from final design drawings for a construction of

P3 Take-off quantities for a range of construction activities

P4 Abstract a range of quantities for construction or civil engineering activities

infrastructure project

M2 Accurately apply a standard method of measurement to the production of quantities

LO3 Interpret the principles and techniques of estimating in compiling a final price

LO3 and LO4

D3 Evaluate estimating techniques used for the different stages of a

project's life cycle

PS Calculate labour unit rates for an estimate by compiling and processing rate build-up data

P6 Calculate all in rates for a range of construction or civil engineering activities

M3 Analyse the factors that have an effect upon the compilation of unit rates for an estimate

LO4 Prepare an estimate for a work activity

P7 Produce a comprehensive estimate for a work section or activity

P8 Explain the reasons for the level of variation in estimates received by stakeholders

M4 Compare the techniques used for the formulation of budgets with estimating final design costs

GET UNIT 5 MEASUREMENT AND ESTIMATING FOR QUANTITY SURVEYING - PEARSON BTEC LEVELS 4 AND 5 HIGHER NATIONALS IN QUANTITY SURVEYING ASSIGNMENT HELP SERVICE UNDER BUDGET - ORDER TODAY FOR EXCELLENCE!!

RELATED COURSES & ASSIGNMENT SERVICE!!


COMMENTS(0)

LEAVE A COMMENT


Captcha

 

 

Are You Looking for Measurement and Estimating For Quantity Surveying Assignment Help?


Access our Pearson BTEC Levels 4 and S Higher Nationals in Quantity Surveying Assignment Help Services for its related academic units such as:-

  • Unit 5 Measurement & Estimating for Quantity Surveying Assignment Help
  • Unit 2 Construction Technology Assignment Help
  • Unit 7 Quantity Surveying Practice Assignment Help
  • Unit 11 Surveying, Measuring & Setting-out Assignment Help
  • Unit 3 Construction Practice & Management Assignment Help
  • Unit 10 Construction Information Assignment Help
  • Unit 4 Law & Legal Frameworks for Quantity Surveying Assignment Help
  • Unit 9 Legal & Statutory Responsibilities in Construction Assignment Help
  • Unit 8 Construction Economics & Sustainability Assignment Help
  • Unit 6 Tender & Procurement Assignment Help